The situation
The property in San Jose needed a separately metered ADU / separate meters for each unit / added capacity for 3. PG&E bills each unit from its own meter, so every unit needed its own meter and main breaker, all fed from one utility service.
What a hot gutter is
A hot gutter is a wireway installed on the line side of the meters, ahead of them. The utility’s service conductors land in the gutter, and taps run from there to each meter socket. Because the conductors inside are unmetered, PG&E seals the gutter, and it has to follow PG&E’s Greenbook requirements for layout, access and sealing. It’s a common way to serve several meters from one service drop or lateral without a factory-built multi-meter panel.
What we did
Prepared a load calculation for the whole property, plus each unit / the new ADU
Installed a 320A continuous-rated service (Class 320 meter base, the standard utility equipment for a 400A residential service)
Installed the hot gutter with taps to 3 meter-main combinations
Sized the service and tap conductors per the NEC, with [conductor size/type] [in conduit/underground]
Coordinated with PG&E on design approval, sealing and meter set
Each unit now has its own meter and main breaker on one 320A service, with room for Future Loads